Concrete pads for home batteries in WA

Check whether you can use an existing slab, what PSW allows for a new concrete pad and what to confirm before you book the work.

A home battery installed beside an open residential garage.
In this article

A garage or side path can look like it has plenty of room for a home battery. Start by looking at what the battery will stand on. If the spot is soil, gravel or paving, allow for a concrete pad before the electrician arrives.

An existing slab may be enough

For new PSW Energy sales from 16 November 2026, we require a concrete pad at the proposed location for a floor-mounted battery if there is no suitable concrete slab. If there’s already a slab, show us the whole area and its edges. We’ll check whether it can support the specified battery and take any fixings the manufacturer requires. If your model allows wall mounting, we’ll assess the wall and mounting arrangement separately.

The pad dimensions we start with

Measure from the outside of the installed battery system. If your quote includes more than one stack or cabinet, ask the designer to confirm their combined footprint before you measure.

PSW’s starting dimensions for a new concrete pad
Part of the padWhat to allow
Each side150 mm beyond the battery on the left and right
Front150 mm beyond the front of the battery
Concrete thickness100 mm
Rear and overall depthConfirm both with PSW for your model and location

For the width, add 300 mm to the installed battery width. These dimensions describe the concrete base. Your electrician also checks the manufacturer’s mounting instructions and the clearances and protection required at your property.

Leave room for the car

In a garage or carport, show us where the car normally parks and how it gets in and out. A battery can fit beside a wall and still be in the path of a bumper or door. Your electrician may need to allow for a protective barrier such as bollards, or recommend another spot. Confirm the barrier position and who will supply it before anyone orders concrete. Our guide to home battery placement covers the other checks that can affect where the system goes.

Before you book the concrete work

  1. Send a wide photo of the proposed spot. Include the floor or ground, nearby walls and openings, and any step or slab edge. Include the normal parking position if a vehicle uses the space.
  2. Get the position and dimensions confirmed for your battery. Photos help us assess the site remotely. We’ll arrange a site check if we need one to confirm the base, access or proposed protection.
  3. Check your written scope. Concrete and other site preparation sit outside PSW’s standard installation scope. Confirm who will arrange the work, when it needs to be ready and any separate cost. See what can change your installation price.